Galldris Ashford Designer Outlet

Ashford

Project Introduction

Galldris Construction is working directly with the Principal Contractor, McLaren. This second phase of construction will enable McArthurGlen to add up to 50 new luxury and premium brands to the existing names already trading in the famous tented shopping centre designed by Lord Richard Rogers.

An additional 500 jobs will be created to bring Ashford Designer Outlet’s total workforce to 1,500 making this one of the largest of its kind.

The Challenge

Galldris will be delivering the substructure and RC cores for this scheme along with the construction of a new 1200 space car park commencing in April 18 and will be on site for 70 weeks. Former industrial use of the land has created some challenging ground conditions byway of contamination. Galldris will undertake the remediation and disposal of 40,000m2 of new floor slabs and hard standings and construct a new river crossing.

Client

McArthur Glen

Galldris Value

£9.6m

Services

  • Groundworks
  • External Works
  • Paving

Duration

On going 2018

Ashford

Outlook

Scheduled to open in Autumn 2019, the extension will deliver up to 50 additional premium and luxury brands, a new food piazza, 725 further parking spaces as well as a new events space and redesigned children’s play area. The expansion will also include the installation of Europe’s largest living wall structure and many of the stores in the new phase will be clad in tens of thousands of plants, all stacked vertically.
5

Client:

McArthur Glen

Galldris Value:

£9.6m

Location:

Ashford

Duration:

70 Weeks